‘Dismay’ at lack of flood relief measures in Waterford village as residents ‘abandoned’


Cllr Declan Barry spoke on the subject of Passage East at the November meeting of the Waterford Metropolitan District
A local councillor has expressed his “dismay” at the lack of flood relief measures in a village in County Waterford.
Independent councillor Declan Barry spoke on the subject at the November meeting of the Waterford Metropolitan District.
Cllr Barry said: “I’d just like to express my dismay at the villagers in Passage East after being abandoned after the bad flooding that we had back 10 months ago now.
“I now believe they are going into the winter on their own. Nothing has changed, no improvements, no flood doors.
“I wish they were being left high and dry but unfortunately, they won’t be high and dry if this bad weather continues. So, [I am] very disappointed in the OPW and I will say the council somewhat as well.”
In response, Gabriel Hynes, Director of Services at Waterford City and County Council, outlined the work that is planned for the village.
Mr Hynes said: “Just in relation to Passage East and flood barriers, we have a nice bit of work done. It was our intention as a local authority to undertake a grant scheme.
“We have all the information gathered from the houses both in Passage and Tallow. It was our wish that we would give a grant to individual householders to undertake the work themselves and we’d cover the costs.
“The OPW have advised against that and they’ve advised us to do something for all the houses and procure the necessary works through a contractor.
“So we’ve commenced that work now but it will take a lot of time to do the circuit work and go to procurement so it will probably be six months away before we get those barriers installed.”
He went on to outline what the council believes the long-term solution to the issues in Passage East is.
“I’d also advise you that the long-term solution for Passage is to upgrade the culvert and to deal with the surface water drainage.
“We have consultants appointed there. You would be aware that surface work was carried out there recently in relation to the underground.
“So we would be hopeful that we would be commencing the contract in the next year, in relation to upgrading the pipework at Passage.”
Mr Hynes concluded by saying that the aforementioned work is all happening in the background at present.