New train station in Waterford city ‘on schedule’ to open at end of next year

The new Transport Hub on the North Quays in Waterford cityplaceholder image
The new Transport Hub on the North Quays in Waterford city

An update on the Transport Hub was provided at the June plenary meeting of Waterford City and County Council

The new train station in Waterford city is “on schedule” to open at the end of next year, a council meeting has heard.

Senior Engineer Seán Dobbs provided an update on the Transport Hub on the North Quays at the June plenary meeting of Waterford City and County Council.

Mr Dobbs said: “At the moment, the contractor is filling out the offices, toilets, lifts and other public facilities.

“The various information and communication systems for the train station are being commissioned.

“The way-finding signage for visitors is being installed. We’re finishing off the northern plaza and the set down areas.

“We’re also doing the western footbridge at Dock Road as well. You can see some of the finishing there on the upper facades.”

He went on to say that whilst there is still work to be done, the building is starting to take shape.

“I think it’s starting to look quite well. It’s starting to take shape. There’s some work to be done there but the works should be finished in July or August.

“A big part of the train station is the commissioning of the various systems that need to go into operation.”

Mr Dobbs continued by outlining the various regulatory checks that the train station will have to undergo in advance of its opening.

“The train station is complete this year, we then have to get our final regulatory approvals in order to open the train station, the new tracks and the new signalling equipment for public use.

“So you have your certification under the buildings regs, disability certification, EU directive certification, commission for railway regulation, that’s to authorise it under safety and Irish Rail then will give their notification of completion.

“At this point, the train station can open to the public, so we’re on schedule to complete that in Q3 of next year.”

However, he highlighted that the opening of the train station will depend on the progress of the private development.

Mr Dobbs said that Harcourt Developments are expected to start work on the SDZ development at the end of this year.

It is expected to take them 12 months to complete the integration works that are required before the train station and sustainable transport bridge can open.