Cost to taxpayer of Waterford’s North Quays project now estimated at over €230 million


An update on the costs of the project was provided at the June plenary meeting of Waterford City and County Council
The cost to the taxpayer of Waterford’s North Quays project is now estimated at over €230 million, a council meeting has heard.
Senior Engineer Seán Dobbs provided an update on the costs of the project at the June plenary meeting of Waterford City and County Council.
Mr Dobbs said: “Just on the funding overview, our current estimate of our forecast budget is currently €232.8 million.
“Our current approved funding is €214.1 million. The final business case for the project was approved by the Government in 2022 for €207.4 million.
“We have since secured €6.7 million in additional funding from the Department of Transport. That was for the expanded scope of the flood defence works.”
He went on to outline the reasons why the cost of the project has increased over time.
“That includes all elements of the project going back the last 10 years.
“We’ve had nine enabling works contracts, the main works contract with BAM, consultant contracts, the flood defence scheme, all of the Irish Rail contracts.
“That includes the SET works on the tracks, the drainage works, etc and Irish Rail’s costs. Then, historical acquisitions, planning, professional fees etc.
“The €232.8 million also includes our own risk and contingency, so we monitor budgets continuously.”
Mr Dobbs said it was important to note that the figure given was just the estimated expenditure and didn’t take any income from the project into account.
He went on to explain what the project is costing Waterford City and County Council.
“So in that last pie chart, the council’s contribution was €40.2 million of the €232.8 million.
Again, that’s a projected figure and it includes risk and contingency.
“If you break down that figure for council expenditure, we forecast that about €7.9 million will go towards the sustainable transport bridge, about €3.8 million towards the access infrastructure and about €28.5 million towards the overall railway infrastructure.
“What I mean by railway infrastructure is the train station, track works, all of the flood defence works so that altogether is a very big piece of the work.”
Of the outside funding that the council has secured so far, €101.6m of that has come from the Urban Regeneration and Development Fund (URDF).
Meanwhile, €84.2 million has been provided by the National Transport Authority (NTA) and €6.7 has been provided by the Department of Transport.